9.10.2 Enhancements and Fixes

9.10.2 Enhancements and Fixes

Enhancements

  • Added aging to Unsolicited Change Requests in the Project Summary

Fixes

Project Summary

  • Unsolicited Change Requests in the status of “Reviewed” did not display in the Project Summary

Progress Claim

  • Included “Reviewed” status in the logic used to determine if a Progress Claim is newer (subsequent) or older (previous)
  • When the Amount Claimed is equal to the Total Contract, rounding from previously issued Progress Claims causes the error “The amount claimed is more than the Total Contract”